How a factory-built multiplex goes up

Modules are built indoors at ProFab Ontario while the foundation goes in on your lot. Then a crane day. Timeline is confirmed on consult, not a single number for every job.

01

Address and product

Lot, zoning, and which catalogue model actually fits. Duplex through 12-unit, or custom stacked.

02

Drawings and permits

We coordinate plans and municipal submissions. Site plan if the city requires it.

03

Plant and foundation in parallel

ProFab’s typical plant window is about 10 to 12 weeks. Foundations happen on site at the same time.

Real sixplex crane set ProFab factory line

Crane and plant photos are real process shots. Qualifying new homes are Tarion-registered.